Make Story Points required / mandatory when beginning a Sprint in Agile Jira(Greenhopper)

StackOverflow https://stackoverflow.com/questions/18832538

  •  28-06-2022
  •  | 
  •  

سؤال

I want to require the Story Points field to be filled in, but only before starting all sprints. Our team doesn't evaluate the size when first creating issues so it shouldn't be required that early.

Story points will be optional at start, we'd just want it mandatory before the sprint is started.

Does anything on the Issue-level change when the Sprint starts that an issue is in?

Would this be a configuration change in Jira Agile (formerly Greenhopper) or would this exist elsewhere?

Does the Behaviours plug-in support this functionality?

هل كانت مفيدة؟

المحلول

All that needed to be done was to configure the Estimation Statistic, specifically for Time Tracking.

It needs to be switched from "Remaining Estimate and Time Spent" to "None"(which also means it defaults to your Estimation Statistic for Time Tracking, in my case "Story Points")

https://support.atlassian.com/jira-software-cloud/docs/configure-estimation-and-tracking/