How to determine the story point value in Agile methodology and determine the team velocity? In web search able to get the definition but not the actually process explanation.

有帮助吗?

解决方案

Story Point is estimated during the Sprint Planning by the team members. It's better if each team member discloses the story point simultanously by using Scrum cards.

For example:

Product Manager creates a story to add a facebook like button in the company website. Developer A quotes 4 hours. Developer B quotes 5 hours. QA quotes 3 hours. In the end, the team decided to use 4 hours(or 5 hours) development + 3 hours QA as the story point.

enter image description here

For team Velocity, check this simple explanation.