I am building a KPI in PerformancePoint - SharePoint 2010 and have the following setup:

We have some files that are stored and they have a "Review/Expiry Date" field. Is it possible to get the KPI to display red if the review date is less than todays date?

I thought this might be something simple but it's turning out to be really hard to find a solution that I can use in PerformancePoint.

I can build the functionality into XML but that would then seperate these files from all the other KPI's I have!

Thanks a million in advance for any assistance.

Rich

Was it helpful?

Solution

The answer to your question is heavily dependent on the type of data source you're using. If you have your data in a SQL Server table, it should be trivial to add another column that generates a "days left to complete" or something, and you can set your target thresholds accordingly.

So I would create a table that looks like this:

Item   | Review Date | Days Remaining
Task 1 | 10/01/2011  | 95
Task 2 | 1/1/2011    | -30
Task 3 | 2/28/2011   | 12

The Days Remaining column would just be something like

SELECT DATEDIFF("dd", [Review Date], GETDATE())

If you want to do this in a SharePoint list, you can also accomplish this easily. I created a simple task list and added a Calculated Column called Remaining Days. I used the following formula:

=[Due Date]-[Today]

When you create your KPI, just create a Target for Days Remaining. You want Larger is Better, Green is anything above 5 days, Yellow between 1 and 5, and Red is anything less than 1.

The ease of this really depends on your data source. Good luck.