Question

How would I go about using jtracert to sequence diagram a junit test being run within eclipse?

Was it helpful?

Solution

In the "Run" dialog, select your JUnit configuration and go the "Arguments" tab. Add jTracert parameters to "VM arguments" section (something like -javaagent:/home/dmitrybedrin/work/jtracert/deploy/jTracert.jar)

Click on "Run" button.

You will see the following in the "Console" tab:

jTracert agent started Waiting for a connection from jTracert GUI on port 7007

Now execute jTracert gui and connect to the jTracert agent.

That's it - you will see the sequence diagrams now!

OTHER TIPS

There's a small mistake in my previous answer - you should specify -javaagent:/home/dmitrybedrin/work/jtracert/deploy/jTracert.jar=7007 to "VM arguments" section.