Question

I have a date field in my PWA Projects. I would like to use that date in a workflow to calculate another stage's due date. My thinking is to calculate a new date from the Project Data/Existing date field.

I am using Sharepoint Designer 2013, and when I try to calculate the new date, I add the calculate Action, and choose a value, select Project Data, and choose the Existing Date, but then OK grays out and I cannot use that value as part of the calculation.

Was it helpful?

Solution

The Do Calculate action is not used with date type

It's used with only numbers to can perform +, - ,/ ,*

enter image description here

Meanwhile, to be able to add days to a date field you should use Add Time to Date action as shown below.

enter image description here

Note: in Add Time to Date action specify the period that you need to add to your date and specify your Project Date field as shown below:

enter image description here