I am looking to pull data from PWA into PowerBI. When I add the Project table in, I don't see the Project field "Priority" This is kind of a key field for us and I don't know where it is.

Was it helpful?

Solution

I found it. It is in tasks. If you have a row and the TaskIndex = 0 then that contains the projects priority.