PWA through PowerBI missing Priority
-
26-12-2020 - |
Question
I am looking to pull data from PWA into PowerBI. When I add the Project table in, I don't see the Project field "Priority" This is kind of a key field for us and I don't know where it is.
Solution
I found it. It is in tasks. If you have a row and the TaskIndex = 0 then that contains the projects priority.
Licensed under: CC-BY-SA with attribution
Not affiliated with sharepoint.stackexchange