Question

I am trying to modify an Assignment view in Project Online.

I would like to display the Project Priority in the table portion of the view, but I can only select the Task Priority.

How can I display the Project Priority as a column?

Was it helpful?

Solution

Because of The assignment views used to review details about resource assignments and its Tasks not about the project.

So It's logical behavior, to can't find the Project Field in the fields list at the table portion for these views.


By the way, The Project Priority field is shown in the related views of the Project Center Category like

  • Summary.
  • Work.
  • Cost..... etc

enter image description here

Licensed under: CC-BY-SA with attribution
Not affiliated with sharepoint.stackexchange
scroll top