Question

I am trying to understand the new scrum template of tfs2010. I understand that PBIs are implemented by SBTs. but how is an SBT linked to a sprint. I mean, how do I specify that this SBT belongs to this sprint.

Was it helpful?

Solution

Actually, there is a Product Backlog Item work item type.

You associate the two by setting the Iteration Path of the Sprint work item, then setting the same iteration path on the PBI (or any other work item).

OTHER TIPS

See [Aaron Bjork's session on \BUILD](http://channel9.msdn.com/events/BUILD/BUILD2011/TOOL-793T) on this subject to understand this better.

I believe he is using the Agile process template, but the same principles can be applied to the scrum template.