Assuming the network diagram is correct, a->c->f
has a cost of 6 + 6 + 9 = 21. a->d->g
has a cost of 6 + 7 + 7 = 20. So a->c->f
would be the longest (and hence critical) path.
Please note that I did not take into account any of the crash durations, costs, etc. from the original table. People should work 40-hour work weeks, not "crash". :)