Question

In the schedule problem P||Cmax given:

n - number of tasks to schedule
m - number of machines
vector p - keeps times of working for each of n tasks.

How is p is defined each time?

Namely, is it an integer or a floating point number?

Était-ce utile?

La solution

Talking about classical problem, execution times are integers. Using scaling, we can expand it to the case of rational execution times - it's good enough for approximations of real problems.