I am using TFS 2013 and the Scrum 3.0 project template.

I have recently upgraded our TFS 2013 server to TFS 2013 update 2, in order to remove the weekends from our Sprint burndown graph.

The problem I have now is that the 'ideal' line no longer finishes at zero. Does anyone know how I can fix this?

enter image description here

役に立ちましたか?

解決

Thanks for the report of this. We have had a bug on this in TFS 2013 Update 2 RC that we fixed for RTM. Could you please verify your TFS version?

Ewald Hofman - TFS Program Manager