質問

I have run into a scenario where I create a process instance and subsequently start process on the task.

Is there a way to update the task status using the kContext from within the bpmn? (Moving the task from Reserved to In Progress)

Thanks.

役に立ちましたか?

解決

Upon investigation my concept was flawed.

The solution was to create a custom WorkItemHandler to perform my desired operation.