The "Split in Progress Tasks" option must be selected or the Stop field will be read only. File>Options>Schedule>Scheduling options for this project>Split in progress tasks. Checking that box solved the problem.
Writing to the Task.Stop field Microsoft Project
-
31-07-2022 - |
문제
I am attempting to take status off of a task by setting the task.stop field to an earlier date using vba. I am getting a "Runtime Error 1101: The argument is not valid."
I have tried the following two lines of code:
Task.Stop = CurrentProj.StatusDate
and
Task.SetField FieldID:=pjTaskStop, Value:=CurrentProj.StatusDate
Current values are:
CurrentProj.StatusDate = 10/31/2013 17:00:00
Task.Stop = 11/5/2013 17:00:00
both are of Variant/Date DataType
I could not find and use of the Stop field in any forums. Thanks for any help you can provide.
해결책
제휴하지 않습니다 StackOverflow