문제

We just updated our TFS2008 to TFS2010. On the daily builds on TFS2008 I had made an extra functionality in the TFSBUILD.proj so that on Partially Succeeded builds, a work item was created.

So if a build was going right, but one ore more unit tests did fail, a work item was created.

This was done by putting some extra xml in the TFSBUILD.proj. But after upgrading to TFS2010, this functionality was gone. And because the whole build architecture is changed in TFS2010, i cannot find out how to do this in... tfs2010.

So the question is: How to get a work item if a dialy build is partially succeeded.

도움이 되었습니까?

해결책

After some extensive searching I found the solution.

I opened the UpgradeTemplate.xaml in BuildProcessTemplates, this is the one VS had created during the upgrade from TFS2008 to TFS2010.

Almost at the end of the workflow there is an if-statement called: If TestStatus = Unknown

The Else is empty, I put there an OpenWorkItem activity. So now on an unit test failure, a work item is created.

See also: http://blogs.msdn.com/b/lab_management/archive/2010/02/25/creating-a-bug-on-test-failure.aspx

다른 팁

I've had a look through the defaulttemplate.xaml, and it looks like you're going to have to play around with that to replicate what you have currently, on the plus side it doesnt look too hard. It's just a xaml file so opens in a VS designer, should be ok for what you need.

Might want to make a copy and set the template in your build definition > process > build process template while you play :)

라이센스 : CC-BY-SA ~와 함께 속성
제휴하지 않습니다 StackOverflow