Pregunta

I have two questions:

  1. According to this article if I define some future iterations (i.e. iterations with dates set in the future) then I should see them listed on the left hand side under the heading 'Future'. But I don't see anything:

    Product Backlog

  2. I assume this problem is related, but I'm hoping to get the forecasting setup as per this article, but as shown in the screen shot below I'm getting an error.

¿Fue útil?

Solución

Are the future iterations checked? There is a checkbox next to iterations in Iterations window - see screenshot.