Does scrum planning for a iteration 2 come after or before the sprint review (demo/retrospective) of iteration 1?

도움이 되었습니까?

해결책

Normally the sprint review happens immediately after the sprint has finished and the planning for the next iteration comes sometime after that.

다른 팁

The normal order for a sprint is this:

  1. Sprint Planning
  2. Dev (with Daily Scrums)
  3. Sprint Review
  4. Sprint Retrospective

Repeat until project complete

So, to answer your question, Sprint Planning for iteration 2 will occur after the Sprint Review and the Sprint Retrospective for Sprint 1.

Hope that helps.