Pergunta

Does scrum planning for a iteration 2 come after or before the sprint review (demo/retrospective) of iteration 1?

Foi útil?

Solução

Normally the sprint review happens immediately after the sprint has finished and the planning for the next iteration comes sometime after that.

Outras dicas

The normal order for a sprint is this:

  1. Sprint Planning
  2. Dev (with Daily Scrums)
  3. Sprint Review
  4. Sprint Retrospective

Repeat until project complete

So, to answer your question, Sprint Planning for iteration 2 will occur after the Sprint Review and the Sprint Retrospective for Sprint 1.

Hope that helps.

Licenciado em: CC-BY-SA com atribuição
Não afiliado a StackOverflow
scroll top